Glenmont Roundabout Update

Glenmont Roundabout Update Nighttime work will resume Wednesday evening through early Saturday morning as overnight crews will begin forming the circle of the roundabout. Pavement excavation and paving will occur on the Glenmont Road side of the roundabout. Expect to drive on gravel surfaces for one to two days late in the week. Paving will…

Glenmont Roundabout Update and Benderson Development Work

No nighttime work is expected on the Glenmont Roundabout this week. Excavation will continue at the corner of Town Squire Plaza (Price Chopper) to widen the intersection for the roundabout, add drainage and prepare to install curb and asphalt. Relocation of Verizon overhead utility lines will continue. Curb and sidewalk work continues along Glenmont Road.…

Glenmont Roundabout Update for the week of September 20

Utility and Sidewalk Work Continue WHAT’S HAPPENING NOW An overnight water service interruption scheduled for the week of September 20-24 has been rescheduled for a second time, and is now expected to take place on one overnight period during the week of September 27 – October 1. Affected property owners will be contacted by the…

Dates rescheduled for water outage in Glenmont

Update to water outage in Glenmont

Glenmont Roundabout Work Week of Sept. 6 and beyond

Overnight work will continue through Sept. 11 on storm drains and overhead lines. Water service will be interrupted week of Sept. 13.

Glenmont Roundabout Update

Construction on the Glenmont Roundabout continues next week with overnight work talking place Aug. 30 starting at 7 p.m. During labor day weekend work will be suspended Sept. 2-7.

Glenmont Roundabout Update

WHAT’S HAPPENING NOW Week of August 23 Minor water line work is underway near CVS Pharmacy. There will be no loss of water service. Sidewalk preparations continue. Underground gas line relocation work continues. Crown Castle and First Light Fiber are relocating overhead utility lines. A shoulder barrier will be installed along Glenmont Road. Traffic Impact:…

Glenmont Roundabout Construction Begins Aug. 16

Lane shifts and traffic slow-downs with movement of equipment in and out are to be expected.

Glenmont Roundabout Update

Construction pre-work update

Employee Retention Tax Credit

Employee Retention Tax Credit Puts money back into your business Though the Employee Retention Tax Credit (ERTC) is expiring at the end of 2021, there’s still time for eligible businesses to claim the credit. Employers are still able to take advantage of the employee retention credit against applicable employment taxes and qualified wages paid to…