Skip to content

Government Relations

Glenmont Roundabout Winter Button Up

WHAT’S HAPPENING NOW Week of December 6 No nighttime work is scheduled for this week.Concrete will be poured to complete the “splitter” islands, which divide incoming and outgoing roundabout traffic.Permanent roundabout signage will be installed.Sidewalk installation will continue around the perimeter of the roundabout. Any unfinished sidewalks will be completed with temporary pavement for the…

Glenmont Roundabout Paving Prep Dec. 2 & 3

Beginning Wednesday, Dec. 1, the contractor will be milling pavement on all travel lanes leading to the Glenmont Roundabout. On Thursday, Dec. 2, the contractor will pave those same travel lanes for winter shutdown. This will cause driving delays during non-peak hours only on today and tomorrow between 9 a.m. and 4 p.m. Please see…

UPDATE on Glenmont Roundabout Paving

Traffic delays anticipated for Thursday, November 18 through Saturday, November 20 are canceled. Final top course paving is now tentatively scheduled early in the week of November 29, weather-permitting. The Town of Bethlehem will provide notification about the top course paving schedule via social media, e-newsletter and local news as more information becomes available.

Paving to begin at the Glenmont Roundabout

paving at the Glenmont Roundabout

Glenmont Roundabout Traffic Moving

Nighttime work not expected this week. The center island of the roundabout will have curb installed on Monday and Tuesday. Concrete for the center island truck apron will be poured on Wednesday and Thursday. Curbing for “splitter” islands, which divide incoming and outgoing roundabout traffic, will be installed on all sides of the roundabout beginning…

Glenmont Roundabout Update

Glenmont roundabout update

Road work at Four Corners Delmar Nov. 1-14

Road work at Four Corners Delmar Nov. 1-14 Work will replace portionof sewer line Road work will be conducted on Kenwood Ave. south of the four corners starting Monday Nov. 1. Traffic will be diverted and down to one lane in some directions. This work is being done in order to replace damaged section of…

Glenmont Round About Update

Nighttime work will resume Monday evening through early Saturday morning as overnight crews will install pavement, curb and temporary road striping at the roundabout. Curbs will be installed on the outer edge of the roundabout late in the week. Sidewalks will be installed in front of CVS and Town Squire Plaza. Foundations for overhead light…

Glenmont Roundabout Update

Glenmont Roundabout Update Nighttime work will resume Wednesday evening through early Saturday morning as overnight crews will begin forming the circle of the roundabout. Pavement excavation and paving will occur on the Glenmont Road side of the roundabout. Expect to drive on gravel surfaces for one to two days late in the week. Paving will…

Glenmont Roundabout Update and Benderson Development Work

No nighttime work is expected on the Glenmont Roundabout this week. Excavation will continue at the corner of Town Squire Plaza (Price Chopper) to widen the intersection for the roundabout, add drainage and prepare to install curb and asphalt. Relocation of Verizon overhead utility lines will continue. Curb and sidewalk work continues along Glenmont Road.…