Construction Continues; and will Hold Labor Day Weekend

WHAT’S HAPPENING NOW

Week of August 30

  • Sidewalks will be installed along Glenmont Road and Route 9W.
  • Stormwater management/drainage work begins.
  • Overnight work will begin taking place on Monday (Aug. 30) evening at 7:00 p.m. to install water line between CVS and Glenmont Centre Square. Water service disruption is expected overnight Wednesday, Sept. 1 to Thursday, Sept. 2. Affected water customers will be limited to Glenmont Centre Square and a few residences along Feura Bush Road, who will be notified of overnight service outages by the contractor 48 hours before service disruption.

Traffic Impact: In daytime hours, lane shifts on Route 9W and single-lane alternating traffic on Glenmont Road. Traffic impacts are anticipated.

In nighttime hours, lane closures will take place during water line work. Expect delays.

WHAT’S HAPPENING NEXT

  • There will be no work between 6:00 p.m. Friday, September 3 and 6:00 a.m. Tuesday, September 7.

Week of September 6

  • Stormwater management/drainage work continues during daytime hours.
  • Sidewalk installation continues along Glenmont Road and Route 9W.
  • Overnight work will take place Tuesday night (Sept. 7) through Saturday night (Sept. 11) to install water mains on Glenmont Road and Route 9W, and stormwater drainage on Route 9W.

Traffic Impact: In daytime hours, lane shifts on Route 9W and single-lane alternating traffic on Glenmont Road. Traffic impacts are anticipated. In nighttime hours, lane closures will take place during water line and drainage work. Expect delays.