WHAT'S HAPPENING NOW Week of August 23 Minor water line work is underway near CVS Pharmacy. There will be no loss of water service. Sidewalk preparations continue. Underground gas line relocation work continues. Crown Castle and First Light Fiber are relocating overhead utility lines. A shoulder barrier will be installed along Glenmont Road. Traffic Impact: Brief single-lane closures or shoulder closures. Flaggers may alternate traffic in each direction during shoulder barrier work. WHAT'S HAPPENING NEXT
Week of August 30 Sidewalk installation begins. Evening and overnight work will begin on water lines near CVS and Price Chopper. Stormwater management/drainage work begins. Charter Communications will relocate overhead utility lines. Traffic Impact: Expect impacts between 7pm-6am during water line work.