Construction begins week of Monday, August 16

WHAT'S HAPPENING NOW

Construction Pre-Work

  • Temporary traffic signals are in place and work zone signage is being installed. Utility pole near Price Chopper will be removed Wednesday.
  • Underground gas line relocation work continues.
  • Utility companies are preparing to relocate overhead cable and fiber lines.

Traffic Impact: No significant impact anticipated.

WHAT'S HAPPENING NEXT

Main Construction

  • Construction will begin the week of Monday, August 16th.
  • New sidewalk preparation will begin to the north (near Price Chopper) and east (near Selkirk Fire Department).
  • Overhead cable and fiber line relocations continue.

Traffic Impact: minor lane shifts, stoppages to get equipment in and out.

  • Water line installation may begin near CVS (work is outside the roadway).

Traffic Impact: road shoulder closures and brief stoppages to get equipment in and out.